Replacing or repairing a chiller means taking the heart of a building's cooling offline, sometimes for days and sometimes for weeks. With the right temporary equipment in place, occupants never notice. Without it, a Texas summer turns a mechanical project into an emergency. Here is how we plan temporary cooling and power for a planned shutdown.
Start from the building's actual peak cooling load in tons (one ton is 12,000 BTU per hour), not the nameplate of the chiller being replaced. Trend data from the building automation system for the same season is the best source. Then decide how much of that load must be carried:
Temporary chillers draw a lot of power, and the building's chiller circuit may be out of service during the work. Confirm the available electrical capacity early. If it is not enough, size a generator for the chiller's full-load and starting demand plus any pumps, and plan the distribution: cables, panels and connection points, refueling, and where the equipment will sit.
Temporary equipment should be delivered, connected and running before the existing chiller goes offline, and stay in place until the new equipment is commissioned and stable. Build in time for testing the changeover in both directions. Rental availability tightens in summer, so reserve equipment early for work between May and September.
When the same contractor runs the mechanical work and the temporary cooling and power, there is no hand-off between companies during the most fragile part of the job. The crew that disconnects the old chiller is the crew that knows exactly what the temporary setup is carrying.
Start from the building's actual peak cooling load in tons (one ton is 12,000 BTU per hour), ideally from building automation trend data for the same season, not from the nameplate of the chiller being replaced. Then decide which spaces need full load, partial load or spot cooling.
A portable chiller connects to the building's existing chilled-water loop, so air handlers and terminal units keep working normally. Spot coolers serve individual rooms and deploy quickly, but they need a place to reject heat and a condensate plan.
Often. Temporary chillers draw a lot of power, and the building's chiller circuit may be out of service during the work. If the available electrical capacity is not enough, size a generator for the chiller's full-load and starting demand plus any pumps.
Early, especially for work between May and September, when rental availability tightens. The equipment should be running before the existing chiller goes offline and stay until the new equipment is commissioned and stable.
Zebrix Group is a service-disabled veteran-owned, TDLR-licensed HVAC and mechanical contractor based in The Woodlands, Texas. We plan and run chiller replacements and provide generator, spot cooler, portable chiller and portable HVAC rentals for shutdowns, emergencies and peak demand across Texas. See how we plan temporary cooling for planned chiller shutdowns, our portable chiller rentals in Houston, or contact us about an upcoming shutdown.