Temporary Power and Cooling During State HVAC Replacements

Zachary (Zack) Butler
Zachary (Zack) Butler

When a state building's HVAC equipment is replaced, temporary cooling and power keep the building working while the old equipment is out and the new equipment is not yet running. The plan comes down to four decisions made before the outage: how much cooling the building really needs during the work, where temporary equipment can sit, how it gets power, and who is responsible for each piece in the contract.

This guide is for state agency facility managers, HUB coordinators and prime contractors scoping chiller, air handler or rooftop unit replacements in occupied Texas buildings. It covers when temporary equipment is worth it, how to size it, the power and permitting questions to settle, and how to write it into the scope so bids come back comparable.

Decide whether the building can go without cooling

Not every replacement needs a temporary plant. Start by listing what the building houses and when the work will happen.

  • Spaces that cannot warm up. Server and telecom rooms, labs, records storage, secure areas, medical spaces and anything with temperature or humidity limits need cooling the whole time.
  • Occupied offices and public areas. In a Texas summer, these usually need cooling too. In mild months, a short outage may be acceptable if it is scheduled around occupancy.
  • Length of the outage. A rooftop unit swap may take days. A central plant replacement can run for weeks once demolition, rigging, piping, startup and commissioning are counted.

If the answer is "some spaces, for weeks," plan a temporary chiller or packaged units for the whole building, plus spot coolers for isolated critical rooms.

Size the temporary equipment from real load

Cooling is measured in tons, and one ton equals 12,000 BTU per hour. Size the temporary plant to the load the building will actually see during the work, not automatically to the nameplate of the equipment being replaced.

  1. Pull trend data. If the building has an automation system, export chilled-water flow and temperatures, or chiller tonnage, for the same season last year.
  2. Separate critical and comfort loads. Critical spaces get full capacity. Some comfort areas may run on partial capacity for a short period if occupants are told in advance.
  3. Account for humidity. In Gulf Coast buildings, holding dew point matters as much as holding temperature. Ask whether dehumidification belongs in the temporary package.
  4. Plan the tie-in. Temporary chillers usually connect to the existing chilled-water loop. Valved connections make that quick. Without them, the loop may need to be drained in sections and fitted with temporary connections, which adds time.

Plan temporary power early

Temporary chillers and pumps need a lot of power. The circuit that fed the old chiller is often the obvious source, but it may be part of the electrical work. When it isn't available, the rental chiller is paired with a generator and temporary power distribution.

  • Size for motor starts. Chillers and pumps draw several times their running current when they start. A generator sized only for running load can trip when the plant restarts. Size from the equipment list and stage restarts where needed.
  • Know the air permit path. In Texas, portable, emergency and standby generator sets can be authorized under TCEQ's permit by rule for portable and emergency engines and turbines (30 TAC 106.511) when they meet its conditions and the general conditions in 30 TAC 106.4. TCEQ says no registration or fee is required, but records showing compliance must be kept on site for a rolling 12-month period.
  • Keep exhaust away from people. Generator exhaust contains carbon monoxide, which the EPA describes as an odorless, colorless and toxic gas. Place generators outdoors and away from air intakes, doors and windows.
  • Plan fuel. Agree on who refuels, how often, and where fuel is stored. Long outages need a written refueling schedule.

Our guide to generator rentals for Texas facilities covers sizing, permits and fuel in more detail.

Work around a state building's rules

Occupied state buildings add constraints that a private job might not have. Settle these with the agency before the rental arrives:

  • Badging, escorts and background checks for crews, especially near secure areas.
  • Where equipment can sit without blocking fire lanes, exits, parking or public entrances.
  • Noise limits and working hours near offices, courtrooms or residential neighbors.
  • Who on the agency side approves shutdowns, changeovers and after-hours work.
  • How occupants will be told about planned temperature changes.

Write it into the scope

Bids are only comparable when every bidder prices the same temporary plan. In the solicitation or the prime's subcontract scope, spell out:

  • The temporary cooling capacity and the spaces it must serve.
  • Whether temporary power is included, and who supplies fuel.
  • The expected rental duration, with a unit price for extra weeks.
  • Who makes the chilled-water and electrical connections, and who removes them.
  • Who monitors the temporary equipment, and the after-hours response time.
  • The changeover sequence from temporary to permanent equipment, including commissioning.

These items also make good interview questions. Our post on questions state facilities should ask HVAC contractors lists more.

Schedule around the season

Replacements that start in spring and finish before peak summer need less temporary capacity. The Atlantic hurricane season runs from June 1 through November 30, so Gulf Coast work that spans those months should include a storm plan for securing temporary equipment and keeping the building powered. The National Hurricane Center posts active advisories.

Estimating temporary power is easier with the equipment list in hand. Prime contractors can rough out generator sizes with GeneratorIQ in the Zebrix Contractor Suite before asking for rental quotes.

Frequently asked questions

Do we need temporary cooling for every HVAC replacement?

No. Short replacements in mild weather, in buildings without critical spaces, can often be scheduled around occupancy. Long outages, summer work and buildings with server rooms, labs or records storage usually need it.

How do we size a temporary chiller?

Use the building's actual load during the work, measured in tons (12,000 BTU per hour each), from automation trend data where possible. Give critical spaces full capacity and decide which comfort areas can run on partial capacity.

Does a rental generator need an air permit in Texas?

Portable, emergency and standby generator sets can be authorized under TCEQ's permit by rule, 30 TAC 106.511, if they meet its conditions and those in 30 TAC 106.4. TCEQ says no registration or fee is required, but compliance records must be kept on site.

Who should provide the temporary equipment, the prime or a rental company?

Either can work. What matters is that one party is responsible for sizing, connection, monitoring and changeover, and that the scope says so.

About Zebrix Group Inc.

Zebrix Group Inc. is an SBA-certified service-disabled veteran-owned small business (SDVOSB) and a Texas VetHUB-certified vendor (VID 21829539) based in The Woodlands, TX, serving Greater Houston and Texas. We hold TDLR Air Conditioning & Refrigeration Contractor license TACLA00169073C, self-perform HVAC and mechanical work, and provide temporary cooling for chiller shutdowns, portable chiller rentals and generator rentals. See our capabilities or contact us.


About the author: Zachary (Zack) Butler is the founder and CEO of Zebrix Group Inc. and a U.S. Navy veteran. He builds Pulsix AI, one system for a building owner's buildings, work, money and risk.

Get field notes like this monthly: subscribe to the Zebrix Insights Newsletter.

Share this post