When a state building's HVAC equipment is replaced, temporary cooling and power keep the building working while the old equipment is out and the new equipment is not yet running. The plan comes down to four decisions made before the outage: how much cooling the building really needs during the work, where temporary equipment can sit, how it gets power, and who is responsible for each piece in the contract.
This guide is for state agency facility managers, HUB coordinators and prime contractors scoping chiller, air handler or rooftop unit replacements in occupied Texas buildings. It covers when temporary equipment is worth it, how to size it, the power and permitting questions to settle, and how to write it into the scope so bids come back comparable.
Not every replacement needs a temporary plant. Start by listing what the building houses and when the work will happen.
If the answer is "some spaces, for weeks," plan a temporary chiller or packaged units for the whole building, plus spot coolers for isolated critical rooms.
Cooling is measured in tons, and one ton equals 12,000 BTU per hour. Size the temporary plant to the load the building will actually see during the work, not automatically to the nameplate of the equipment being replaced.
Temporary chillers and pumps need a lot of power. The circuit that fed the old chiller is often the obvious source, but it may be part of the electrical work. When it isn't available, the rental chiller is paired with a generator and temporary power distribution.
Our guide to generator rentals for Texas facilities covers sizing, permits and fuel in more detail.
Occupied state buildings add constraints that a private job might not have. Settle these with the agency before the rental arrives:
Bids are only comparable when every bidder prices the same temporary plan. In the solicitation or the prime's subcontract scope, spell out:
These items also make good interview questions. Our post on questions state facilities should ask HVAC contractors lists more.
Replacements that start in spring and finish before peak summer need less temporary capacity. The Atlantic hurricane season runs from June 1 through November 30, so Gulf Coast work that spans those months should include a storm plan for securing temporary equipment and keeping the building powered. The National Hurricane Center posts active advisories.
Estimating temporary power is easier with the equipment list in hand. Prime contractors can rough out generator sizes with GeneratorIQ in the Zebrix Contractor Suite before asking for rental quotes.
No. Short replacements in mild weather, in buildings without critical spaces, can often be scheduled around occupancy. Long outages, summer work and buildings with server rooms, labs or records storage usually need it.
Use the building's actual load during the work, measured in tons (12,000 BTU per hour each), from automation trend data where possible. Give critical spaces full capacity and decide which comfort areas can run on partial capacity.
Portable, emergency and standby generator sets can be authorized under TCEQ's permit by rule, 30 TAC 106.511, if they meet its conditions and those in 30 TAC 106.4. TCEQ says no registration or fee is required, but compliance records must be kept on site.
Either can work. What matters is that one party is responsible for sizing, connection, monitoring and changeover, and that the scope says so.
Zebrix Group Inc. is an SBA-certified service-disabled veteran-owned small business (SDVOSB) and a Texas VetHUB-certified vendor (VID 21829539) based in The Woodlands, TX, serving Greater Houston and Texas. We hold TDLR Air Conditioning & Refrigeration Contractor license TACLA00169073C, self-perform HVAC and mechanical work, and provide temporary cooling for chiller shutdowns, portable chiller rentals and generator rentals. See our capabilities or contact us.